Home  Site Map  Source Page

Kitchen Replacement - 2008

When the 24 year old fridge developed a fault it proved impossible to buy one of similar capacity that would fit in the same height restricted space in the corner of the kitchen. This small but insoluble problem caused the whole of an otherwise perfectly serviceable 21 year old kitchen to be scrapped and replaced. Yet another case of EU morons and their green policies (better insulated fridges) causing unnecessary expense and waste (trees demolished to make new cabinets).
The best compromise of price, style and delivery dates was found at Wickes and exactly on schedule (29th February 2008) a total of 99 separate packages arrived, all of them in perfect condition and everything present and correct.
Kitchen replacement Preparatory work on the electrics and plumbing began some three weeks before the delivery date. The old cooker is withdrawn from its normal position so that the electrical supply can be transferred to its new place. Kitchen replacement The cabinets are taken away and some tiles are removed so that the 45 amp cable can be moved and hidden.
Kitchen replacement Cabling for the extractor unit, the fridge (which is to go where the cooker used to be), the hob ignition and the floor level heater (to replace the traditional radiator) is installed. Kitchen replacement The old radiator is removed and the floor is excavated so that the pipes to the new heater can be hidden.
Kitchen replacement The cabinets arrive and go into the prepared space relatively easily. Kitchen replacement The work surface is in place and the hole for the hob is cut out supported by an old car jack perched on a wooden box so that it won’t fall when finally cut.
Kitchen replacement The hole is neatly cut but reveals that the cabinet needs some surgery to accommodate the hob as it is a little bit thicker than the worktop. Kitchen replacement The hob is connected to the new gas supply and works once one gets used to twisting the knobs counter clockwise to light them.
Kitchen replacement The oven is connected to the new power supply. It looks too big to go into the hole but slips into place perfectly. Old cooker on garden The old cooker is wrapped in polythene and parked in view of the road to see who will take it first. The Albanians who will use it or the gipsies who will sell it as scrap metal. The gipsies won.
Kitchen replacement The oven is in place and the old hatch, not used for several years, is tiled over and made ready for hidden lighting. Kitchen replacement The first of the wall cabinets and the extractor unit are in place. The new fridge is where the cooker used to be. Some plain tiles are removed to accommodate decorative ones taken from places that will be covered by cabinets.
Kitchen replacement Most of the doors go on but the worktop is not yet trimmed to size and remains a hazard to anyone who is working low down and gets up unwarily. Kitchen replacement The cooking side of the kitchen begins to take shape and is fully functional.
Kitchen replacement The plumbing installed by the builder in 1987 was untidy and inconvenient despite small modifications. Condensation on the cold pipes was a problem as was the need to access taps to control supplies to the front and rear gardens. As a result, the under-sink cupboard was close to unusable. The main supply came in via a hole in the foundations and nearly three feet deep. It was subsequently filled with expanding foam. Kitchen replacement The old larder housed the electricity distribution unit and hid the main drainage system. It had been heavily butchered by the builder to accommodate the cables and pipes. Its side panel had been tiled over some eight or ten years ago to make it look a more permanent structure which was fortunate as it provided a supply of spare tiles for use elsewhere.
Kitchen replacement All the main electricity cables and drainage pipe are exposed. Kitchen replacement All the under-sink plumbing is removed and replaced as compactly as possible at the back of the washing machine’s space. Any condensation is therefore removed outside the under-sink cupboard.
Kitchen replacement The pipes and cables behind the larder are rearranged so that the new larder fits in with only minor butchery none of which impinges on the inside of the cupboard. It takes a mere four hours to wiggle into position with everything that should be horizontal or vertical exactly that. It takes another few hours to reconnect the electricity distribution unit. Kitchen replacement The cold water pipes going to and from the water softener are enclosed in 32mm plastic pipe and centred within them with plastic supports and then filled with expanding foam fed in from small holes drilled into the pipe. That should thoroughly fix the condensation on those two pipes which run the whole length of the kitchen behind the new cabinets.
Kitchen replacement Screwing the cabinets to the wall and to each other is not difficult although as with the other side, it reveals that the floor goes slightly downhill. Kitchen replacement The worktop is put in place. Wickes computer fails to notify anyone that it is not long enough to fill the space and will need to be jointed at the far end. In some ways that is good because cutting it exactly to size to fit between two immoveable walls would not be easy.
Kitchen replacement The sink and tap are installed, an operation that required considerable hidden modification to the cupboard as although it claimed to fit within a 600mm cupboard it actually required a full 600mm width and 600mm cupboards inevitably lose more than 30mm due to the thickness of their side panels. It will take quite some time to get used to the right hand draining board which was chosen to maximise the uninterrupted length of work surface. Kitchen replacement The under-sink plumbing is minimal with almost no copper pipe visible in the hope of obtaining a big reduction in condensation. The vertical ‘pipe’ hanging between the two main waste pipes is the box spanner that releases the tap, tied to a pipe so that it doesn’t get lost.
Kitchen replacement The doors are put on the cabinets and things are almost back to normal although many finishing jobs still need to be done.   Lots of odd jobs still to be done. Tiling, floor, lights, cornices, plinths and heater to name but a few.


Top